click here for printer friendly version
Dakota Ridge Board of Directors Meeting
June 4, 2025 at 10am via Zoom
Present: Ron Lemieux, Carrie Hayden, Scott Prochazka, Holly Van Deursen
Others Present: Dana Thorne (ARC), Thomas David (Eric Smith & Associates), Andrea Wilhelm (CPG), and joining ~1015am Sarah Jones (ARC)
Architectural Review Process
The meeting was called to order at 10:03am and Andrea introduced those present to Thomas Davis, the consulting architect from ESA. The purpose of the meeting was to discuss potential changes to the current architectural review process and the corresponding sections of the Design Guidelines. Section 8.1 of the Covenants places responsibility for reviews of proposed construction projects and the creation and maintenance of our Design Guidelines on the ARC. Section 6.1 of the Covenants, however, places the responsibility for deciding how to enforce the ARC’s decisions and recommendations on the Board. Over time, the nature of the review process used by the ARC has changed and the Board and the current ARC have identified ways to potentially improve the process and make it easier for the ARC to perform the reviews described in Section 8.1 of the Covenants.
The Board asked Thomas David to outline the services ESA is currently providing to Dakota Ridge. Thomas detailed that ESA has been serving in an advisory role to verify that the Lot Owner’s submittal is complete and meets general architectural standards and the materials requirements of our current Design Guidelines. He reported that ESA does not provide any further supervision or review of the project once construction has commenced, nor does ESA provide any approval or opinion on whether all Covenants are satisfied or whether any supporting documents, such as soils reports or engineering documents have been properly prepared., Thomas suggested that a construction retainer/compliance deposit is one way to financially incentivize owners to be proactive in oversight of their construction activities and minimize deviations from the approved plans. He also suggested requiring an ILC (Improvement Location Certificate) or IFC (Improved Foundation Certificate) early in the foundation process before any vertical building takes place which verifies the structure has been placed appropriately in accordance with the plans.
Carrie asked Thomas to elaborate on what the County reviews during the construction process. Thomas explained that once plans are permitted, they have essentially been approved by all the necessary departments including Planning, Building, Road & Bridge, etc. He noted the Building Department is primarily focused on human safety and building requirements vs. broader issues like road access, grading, etc. It usually requires a proactive complaint to spur the Planning Dept to go back after approval and do a detailed review. Holly asked about soil stability and whether any of the aforementioned departments examine that topic. Thomas confirmed that all contractors are required to produce a CSMP (construction site management plan) and contained within that document are all the measures and metrics from which the soil needs to be stabilized. Thomas confirmed soil stabilization is not something ESA can evaluate and requires the services and expertise of a civil engineer vs. an architect. It was later suggested that a soils analysis by a certified engineer could be added as a requirement in the ARC approval process.
Scott asked if Dakota Ridge requires site renderings and a civil engineering sign-off. Carrie said it is currently assumed that if the owner’s building is in the envelope, the site lines are compliant. There is no civil engineering approval at the HOA level because this is managed by the County. Holly suggested the applicant’s architect could be responsible for inspecting and enforcing that construction is compliant with submittals to the ARC so the cost falls on the applicant vs. the HOA. Thomas noted this could be difficult if the architect is not local but instead, the GC should be responsible for certifying compliance with the approved plans at various checkpoints/reviews. Ron noted that he would also like ESA to conduct a site visit during the plan submittal process in order to provide an opinion solely to the ARC on the suitability of the proposed home on the lot and its general aesthetic fit with neighboring properties. Thomas clarified that in his opinion, each homeowner ultimately has the right to build anything compliant with the Covenants Design Guidelines and that he did not view this as the outside architect’s role or responsibility. All parties agreed that a pre-submittal meeting would also be beneficial in order to discuss some of the contextual conditions of the lot that might influence design plans and prevent some of the issues that have arisen in recent construction projects within the HOA.
Holly asked if Thomas had seen HOAs establish height or position requirements for ridge line lots relative to some complaints she has received about the Lot 43 construction. He said the County does have ridge line regulations and encouraged the HOA to seek legal counsel before establishing limitations on certain lots that might require a building envelope change in order to meet new ridge line regulations.
The ARC will consider the topics discussed in this meeting as they revise our Design Guidelines.
Around 10:30am, Carrie, Sarah, Dana and Thomas left the meeting and the remaining Board members had some additional discussion in regards to Lot 43 where the primary issues at hand relate to soil stability and the retaining wall construction and height. Ultimately the ARC will be responsible for resolution of this matter once the owner submits the full engineering plans.
Lot 28 Building Envelope Change
It recently became apparent that the home on Lot 28 was built outside of the building envelope 30 years ago without record of County or HOA approval that the envelope was moved. The owner is currently under contract to sell but is facing an objection over this issue and needs the change recorded with the County and therefore it has been submitted to the HOA for formal approval. All three of the owners of adjacent Lots 27, 29 and 25 were notified on Friday of the proposed building envelope change submittal and two of three have responded in favor of allowance. Pending no significant objections from the third owner, Ron made a motion to approve the envelope change to accommodate the home structure as it currently exists, noting the Board and adjacent lot owners reserve the right to potentially object in the future to any proposed changes to the existing structure. Holly seconded the motion and Scott also agreed.
Lot 49 Service Line Repair Costs
The Board ran short on time and felt this topic required further discussion at the July 10th Board meeting. Andrea was instructed to go ahead and pay Native from the Dakota Ridge bank account and notify the owners that the financial responsibility for the repair is still under consideration even though the Covenants indicate that all maintenance and repairs between the curb stop and the residence are owner responsibility.
The meeting adjourned at 11:30am.
Recorded by,
Andrea Wilhelm